Tubular piling continues to the ALB ramp on the northern foreshore, with 20 piles installed so far. The final pile on the foreshore will be completed next week but 6 piles in the middle and top of the gabions on the sea defences will have to wait pending diversion of the overhead BT phone cable to the current boathouse.
Sheet piling around the main site will commence next week.
Friday 22 Jan 2021
Works restart after Christmas
Sunday 20 Dec 2020
Ready for Christmas
Monday 30 Nov 2020
Piling completed
Friday 20 Nov 2020
Installing piles for the main building
Monday 9 Nov 2020
Aerial site views
Sunday 1 Nov 2020
Sheet piling continues
Sunday 25 Oct 2020
Start of sheet piling the ILB ramp
Sunday 18 Oct 2020
Piling the north ramp
Sunday 11 Oct 2020
First piles driven into beach
Wednesday 7 Oct 2020
Getting ready for piling