Wells new Shannon boathouse
Wells Boathouse Build

New boathouse build

  Newer post...
Older post...  

Piling the north ramp

Sunday 18 Oct 2020

Tubular piling continues to the ALB ramp on the northern foreshore, with 20 piles installed so far. The final pile on the foreshore will be completed next week but 6 piles in the middle and top of the gabions on the sea defences will have to wait pending diversion of the overhead BT phone cable to the current boathouse.

Sheet piling around the main site will commence next week.


 

Quick progress with piling for the ramp

Quick progress with piling for the ramp
12/10/2020 Mackley

Piling for the ramp

Piling for the ramp
15/10/2020 Mackley

Piling for the ramp

Piling for the ramp
16/10/2020 Mackley

Piling for the ALB ramp

Piling for the ALB ramp
16/10/20 RW

Piling for the ALB ramp

Piling for the ALB ramp
16/10/20 RW

Piling for the ALB ramp

Piling for the ALB ramp
16/10/20 RW

Beach piles in place and temporarily capped off

Beach piles in place and temporarily capped off
20/10/20 MP