The remaining 6 piles for the ALB ramp in the centre and top of the sea defences have been completed. All 27 piles for the ramp are now installed.
Sheet piling has continued around the ILB ramp and edge of the site with about half now installed.
Work driving in tubular piles for the building itself will start shortly but with high winds forecast there may be some days where it is not possible to drive piles in.
Friday 22 Jan 2021
Works restart after Christmas
Sunday 20 Dec 2020
Ready for Christmas
Monday 30 Nov 2020
Piling completed
Friday 20 Nov 2020
Installing piles for the main building
Monday 9 Nov 2020
Aerial site views
Sunday 1 Nov 2020
Sheet piling continues
Sunday 25 Oct 2020
Start of sheet piling the ILB ramp
Sunday 18 Oct 2020
Piling the north ramp
Sunday 11 Oct 2020
First piles driven into beach
Wednesday 7 Oct 2020
Getting ready for piling