Wells Boathouse Build

New boathouse build

  Newer post...
Older post...  

Sheet piling continues

Sunday 1 Nov 2020

The remaining 6 piles for the ALB ramp in the centre and top of the sea defences have been completed. All 27 piles for the ramp are now installed.

Sheet piling has continued around the ILB ramp and edge of the site with about half now installed.

Work driving in tubular piles for the building itself will start shortly but with high winds forecast there may be some days where it is not possible to drive piles in. 

 

Sheet piling the ILB ramp

Sheet piling the ILB ramp
23/10/20 RW

ILB ramp piling nearing completion

ILB ramp piling nearing completion
23/10/20 RW

Top row of piles for the ALB ramp in position at the top of the bank

Top row of piles for the ALB ramp in position at the top of the bank
28/10/20 Mackley

Sheet piling being added around the boathouse site

Sheet piling being added around the boathouse site
30/10/20 Mackley

Sheet piling being added around the boathouse site

Sheet piling being added around the boathouse site
30/10/20 Mackley