Monday 9 Nov 2020

Sheet piling has continued through the week and is now nearly complete. There was also an opportunity to use the crane bucket for some aerial shots of the site. 

Piling for the new boathouse building is due to start soon. 16.5m and 18m tubular steel piles will be driven through the newly made-up site level into solid ground below the beach.

 

Sheet piling around the southern edge of the site

Sheet piling around the southern edge of the site
4/11/20 MP

View south west over the beach bank

View south west over the beach bank
6/11/20 Mackley

View from crane of site northwards to sea

View from crane of site northwards to sea
9/11/20 Mackley

Sheet piling around site

Sheet piling around site
9/11/20 Mackley

View from crane of site east towards existing boathouse

View from crane of site east towards existing boathouse
9/11/20 Mackley

More work on ILB ramp piling

More work on ILB ramp piling
9/11/20 Mackley