The sheet piling has been completed apart from finishing off the toe piles for the ILB ramp.
Work on piling for the main building has been difficult but is progressing slowly and steadily. Around half the piles have refused to be driven in just with the vibro-hammer rig that has been used up until now. A more powerful impact hammer is being delivered to the site to finish these off.
Storms and high winds have also hindered the work but it is still hoped to have all the piling done and the heavy plant removed from the site before Christmas.
Saturday 20 Feb 2021
Steelwork completed for ALB ramp
Friday 12 Feb 2021
Winter weather and the ALB ramp
Friday 29 Jan 2021
Drainage and service ducts installed
Friday 22 Jan 2021
Works restart after Christmas
Sunday 20 Dec 2020
Ready for Christmas
Monday 30 Nov 2020
Piling completed
Friday 20 Nov 2020
Installing piles for the main building
Monday 9 Nov 2020
Aerial site views
Sunday 1 Nov 2020
Sheet piling continues
Sunday 25 Oct 2020
Start of sheet piling the ILB ramp