Piling completed

Monday 30 Nov 2020

Piling has remained difficult but was finally completed today with the last tubular pile installed and a remaining few that needed to be driven down level.

Work will now proceed with derigging the crane and arranging for it to be transported away along with the piling rig and hammers. Attention will then switch to completing the ILB ramp and preparing for concrete to be poured, and to final fill and grading on the building area to allow drainage works to start.

 

The more powerful impact hammer being used to finish off stubborn piles

The more powerful impact hammer being used to finish off stubborn piles
25/11/20 Mackley

The more powerful impact hammer being used to finish off stubborn piles

The more powerful impact hammer being used to finish off stubborn piles
26/11/20 RW

Finally the impact hammer drives the last pile in

Finally the impact hammer drives the last pile in
30/11/20 MP

Boathouse piles all in position

Boathouse piles all in position
30/11/20 RW