Wells new Shannon boathouse
Wells Boathouse Build

New boathouse build

  Newer post...
Older post...  

Drainage and service ducts installed

Friday 29 Jan 2021

Work has progressed well despite poor weather conditions including cold, frost, wind and rain and some of the time lost in delays before Chrismas has been caught up.

Concrete works have been completed for the ILB ramp and continued onto the eastern capping beam working south. 

The majority of the underground drainage and service ducts have been installed, allowing capping layers of hardcore to be laid and compacted in preparation for the building concrete works to commence next week.

The building slab will be constructed in segments; with the eastern segment of reinforcement steel being fixed next week while the preparation works and remainder of drainage and service ducts continue on the west side of the building.

Preparation works for the ALB ramp install have also continued. The final row of piles have been trimmed and painted within the tidal windows. The steel framework for the ramp is due to arrive shortly and work will begin installing it. A good proportion of this will be in the tidal area and below the current level of the beach. A mobile crane will be used to offload and position the first two bays of the ramp whilst large excavators will install from the beach and complete required excavations.  

 

Pouring concrete at the top of the ILB ramp

Pouring concrete at the top of the ILB ramp
22/1/21 RW

Pouring concrete for the ILB ramp

Pouring concrete for the ILB ramp
22/1/21 RW

Finishing the top of the ILB ramp

Finishing the top of the ILB ramp
22/1/21 Mackley

Base of the ILB ramp. This will be below the beach level in use

Base of the ILB ramp. This will be below the beach level in use
26/1/21 Mackley

Last section of ILB ramp to go

Last section of ILB ramp to go
26/1/21 RW

Working on the ILB ramp and preparing the main site

Working on the ILB ramp and preparing the main site
26/1/21 RW

Compacting capping layers of hardcore on the main site

Compacting capping layers of hardcore on the main site
27/1/21 Mackley

Main site ready being readied for concrete pour

Main site ready being readied for concrete pour
29/1/21 Mackley

The completed ILB ramp with beach levelled off

The completed ILB ramp with beach levelled off
29/1/21 Mackley