Wells new Shannon boathouse
Wells Boathouse Build

New boathouse build

  Newer post...
Older post...  

Winter weather and the ALB ramp

Friday 12 Feb 2021

A bitterly cold few weeks with heavy snow and severe easterly gales have made conditions hard on site but the contractors have continued to push on.

The concrete works to the capping beam that runs from the ILB ramp to the footpath on the south of the building have been completed apart from a couple of corner sections.

The eastern half of the building slab has been capped with hardcore with the thickenings shaped and a blinding layer of concrete laid. Reinforcement steel and shuttering has been started for most of the eastern section of the building although the snow has been problematic.

More visibly, the steelwork for the ALB ramp has been delivered, lifted over the sea defences into position by a crane and installed on the piles. These underpinnings are almost complete apart from the final bay. As the bottom of the ramp will be well under the beach level, the lower section has been dug out again for installation.

The ALB ramp should be completed in the next few weeks, with precast concrete slabs that will form the surface of the ramp due to arrive in the next two weeks.

On the main site, work will continue on constructing the concrete slab on which the building will sit.

 

Hardcore and concrete layer being prepared on eastern side of the building

Hardcore and concrete layer being prepared on eastern side of the building
3/2/21 Mackley

Concrete capping beam leading from the ILB ramp

Concrete capping beam leading from the ILB ramp
3/2/21 Mackley

Pouring the capping beam

Pouring the capping beam
3/2/21 RW

Pouring concrete for the capping beam towards the southern end of the building

Pouring concrete for the capping beam towards the southern end of the building
3/2/21 Mackley

Craning ALB ramp steelwork into position

Craning ALB ramp steelwork into position
9/2/21 Mackley

Steel supports for the ALB ramp added to the piles

Steel supports for the ALB ramp added to the piles
9/2/21 Mackley

A frozen and snow covered site with work still on-going

A frozen and snow covered site with work still on-going
10/2/21 MP

Steelwork being fitted inbetween snow showers

Steelwork being fitted inbetween snow showers
10/2/21 MP

Bottom of ramp being dug out again ahead of steelwork being fitted

Bottom of ramp being dug out again ahead of steelwork being fitted
10/2/21 MP

Work continues in the snow...

Work continues in the snow...
10/2/21 MP

Steelwork in position on the ALB ramp

Steelwork in position on the ALB ramp
11/2/21 Mackley

Digging out the lower end of the ramp so steelwork can be installed on the piles

Digging out the lower end of the ramp so steelwork can be installed on the piles
12/2/21 Mackley

Steel in place on the main site ready for concrete building slab to be constructed

Steel in place on the main site ready for concrete building slab to be constructed
12/2/21 Mackley

View from the top of the ALB ramp

View from the top of the ALB ramp
12/2/21 Mackley