Wells new Shannon boathouse
Wells Boathouse Build

New boathouse build

  Newer post...
Older post...  

Good progress on building slab

Saturday 6 Mar 2021

Work has gone well this week.

Ground beams to west of the building were poured on Tuesday with shuttering and reinforcement steelwork being set up for the rest of the building slab. With concrete pours scheduled for the following two Thursdays, the building slab will be complete by mid-March as planned.

The temporary new footpath to the beach is now open and has already proved useful in providing much needed space for deliveries and plant movements.

The last precast concrete planks have been installed on the ALB ramp, the foot of the ramp once again being uncovered to allow access. Grouting of bolts and recesses is under way and will be completed soon. Following this, timber baulks will be installed on the sides of the ramp and, in due course, handrailing.

Timber works round the edge of the sheet piles and capping beam are now due to start. Timber and piling plant has arrived and the sand previously piled around the sheet pile wall has been dug away to allow access. The path maintained to allow the lifeboat crew  to get to the existing lifeboat station has been realigned.

Services and tanks are due to be installed on the now much clearer northern part of the site. Once this done, the capping beam can finally be completed between the ILB and ALB ramps.

 

Concrete work progressing well on the west of the site

Concrete work progressing well on the west of the site
1/3/21 Mackley

Final precast concrete planks being installed at the foot of the ALB ramp

Final precast concrete planks being installed at the foot of the ALB ramp
3/3/21 Mackley

Foot of ALB ramp exposed again as final concrete planks are installed

Foot of ALB ramp exposed again as final concrete planks are installed
4/3/21 Mackley

Final precast concrete planks being installed at the foot of the ALB ramp

Final precast concrete planks being installed at the foot of the ALB ramp
4/3/21 Mackley

Grouting the ALB ramp

Grouting the ALB ramp
4/3/21 RW

Fixing the concrete planks into position

Fixing the concrete planks into position
4/3/21 RW

Timber delivered for the terracing/breastwork around the sheet piled area

Timber delivered for the terracing/breastwork around the sheet piled area
5/3/21 RW

Sheet piling and capping beam at perimeter of site exposed ready for timber installation

Sheet piling and capping beam at perimeter of site exposed ready for timber installation
5/3/21 Mackley

Reinforcement steel in place ready for pouring more of the building slab

Reinforcement steel in place ready for pouring more of the building slab
5/3/21 Mackley

Beach being restored at foot of ALB ramp

Beach being restored at foot of ALB ramp
5/3/21 Mackley

West side of site prepared for concrete pour

West side of site prepared for concrete pour
6/3/21 RW

Sheet piled perimeter and capping beam prior to timer terraces being installed

Sheet piled perimeter and capping beam prior to timer terraces being installed
6/3/21 RW