Works restart after Christmas

Friday 22 Jan 2021

Since remobilising after Christmas, the concrete works and service installation have progressed well, with much of the ILB ramp constructed as well as a good proportion of drainage, tanks and service ducts in and around the building slab installed. Preparation for the ALB ramp continues, with filling and cutting down the piles and work to the gabions prior to the installation of the steelwork which is planned to start on 8th February. Concrete works will continue onto the sheet pile capping beam the rest of this month into early February, followed by the concrete works for the giant slab on which the main building will sit.

 

Preparations for the capping beam at the southern edge of the site

Preparations for the capping beam at the southern edge of the site
6/1/21 RW

Footings for the capping beam being constructed around the sheet piles

Footings for the capping beam being constructed around the sheet piles
9/1/21 RW

Drainage chambers being constructed

Drainage chambers being constructed
11/1/21 RW

Concrete works for the ILB ramp

Concrete works for the ILB ramp
15/1/21 Mackley

Concrete works for the ILB ramp

Concrete works for the ILB ramp
15/1/21 RW

Concrete works for the ILB ramp

Concrete works for the ILB ramp
15/1/21 RW

Concreting the lower section of the ILB ramp

Concreting the lower section of the ILB ramp
15/1/21 Mackley

Concrete poured for lower section of ILB ramp

Concrete poured for lower section of ILB ramp
15/1/21 RW

Preparation work for the ILB ramp

Preparation work for the ILB ramp
16/1/21 RW

Drainage and service works on the main site

Drainage and service works on the main site
21/1/21 RW

Service works on the main site

Service works on the main site
22/1/21 Mackley

Cutting and filing works to the piles for the main ramp

Cutting and filing works to the piles for the main ramp
22/1/21 Mackley