Since remobilising after Christmas, the concrete works and service installation have progressed well, with much of the ILB ramp constructed as well as a good proportion of drainage, tanks and service ducts in and around the building slab installed. Preparation for the ALB ramp continues, with filling and cutting down the piles and work to the gabions prior to the installation of the steelwork which is planned to start on 8th February. Concrete works will continue onto the sheet pile capping beam the rest of this month into early February, followed by the concrete works for the giant slab on which the main building will sit.
Sunday 14 Mar 2021
Concrete and timber
Saturday 6 Mar 2021
Good progress on building slab
Friday 26 Feb 2021
Concrete slab started, planks installed on ALB ramp
Saturday 20 Feb 2021
Steelwork completed for ALB ramp
Friday 12 Feb 2021
Winter weather and the ALB ramp
Friday 29 Jan 2021
Drainage and service ducts installed
Friday 22 Jan 2021
Works restart after Christmas
Sunday 20 Dec 2020
Ready for Christmas
Monday 30 Nov 2020
Piling completed
Friday 20 Nov 2020
Installing piles for the main building