Scaffolding has been erected on the west side of the building and a start made on the roof for the new boathouse. This is the area where the ILB will be kept and the gift shop and public engagement space in the new building. The first timber sections of roof have been constructed... these are effectively the interior or underside of the roof which will eventually be clad in a weatherproof material over the top of the planks.
Monday 31 Jan 2022
Beginning to look like a lifeboat station
Friday 31 Dec 2021
Working up to Christmas
Tuesday 30 Nov 2021
Internal works
Friday 29 Oct 2021
Steady progress
Monday 27 Sep 2021
Walls and floors
Wednesday 25 Aug 2021
Roof progress
Monday 2 Aug 2021
Work starts on roof
Monday 19 Jul 2021
Frame completed
Wednesday 23 Jun 2021
Progress with frame