Tuesday 30 Nov 2021

Construction of the new boathouse has continued through November but with much more happening on the inside than the outside! Roof panels, exterior cladding and doors will not be added until the early part of next year so the exterior view is still one of plywood walls and polythene sheeting over the windows. It is intended to fit temporary doors made with plastic sheeting to protect the interior from the winter weather.

Inside, underfloor heating and then screed floors have been installed and a start made on internal walls both on the ground floor and on the first floor. Electrical cabling has been installed and the building now has its own electricity. Temporary lights are being installed outside to light the beach so the crew can safely make their way across to the current boathouse in the dark.

Another step forward is that the terracing has been planted up with marram grass kindly donated by the RSPB. Alice Skehel, RSPB Little Tern Project Manager, explained that the society had been moving marram encroaching on tern nesting sites at Eccles back onto the dunes but had some leftover and, aware of the RNLI's project at Wells, felt it was a sustainable solution to offer it to Wells rather than dispose of it.

If you're passing the site, you may also just glimpse a new staircase from the first floor down into the boat hall. This is a temporary addition to make things quicker and safer for the builders. It does occupy the space where the Shannon lifeboat and launching carriage will go so will in due course be removed and replaced with the proper staircase up to the boarding platform shown on the plans

 

Underfloor heating being installed on the ground floor

Underfloor heating being installed on the ground floor
31/10/21 RW

Underfloor heating being installed on the ground floor

Underfloor heating being installed on the ground floor
31/10/21 RW

Screed floor in place in the crew changing and workshop side of the building

Screed floor in place in the crew changing and workshop side of the building
7/11/21 RW

Interior walls being constructed for the private changing room, loos and shower on the ground floor

Interior walls being constructed for the private changing room, loos and shower on the ground floor
7/11/21 RW

Boat hall looking south, with crew boarding platform in place

Boat hall looking south, with crew boarding platform in place
7/11/21 RW

Internal walls on the first floor being constructed

Internal walls on the first floor being constructed
7/11/21 RW

Site view with new signs and information boards along the beach bank path

Site view with new signs and information boards along the beach bank path
7/11/21 MP

Temporary staircase added from the boat hall to the first floor for the builders

Temporary staircase added from the boat hall to the first floor for the builders
17/11/21 CH

Gift shop and engagement space with part of the first floor viewing platform above

Gift shop and engagement space with part of the first floor viewing platform above
20/11/21 RW

Foam insulation blocks being added to the crew room walls

Foam insulation blocks being added to the crew room walls
20/11/21 RW

Insulating layer being added to external walls on north-east corner of building

Insulating layer being added to external walls on north-east corner of building
20/11/21 RW

Boat hall with temporary grand staircase

Boat hall with temporary grand staircase
28/11/21 RW

Insulating the walls with a layer to prevent heat loss and air leakage

Insulating the walls with a layer to prevent heat loss and air leakage
28/11/21 RW

First layer of wall insulation being added in the crew changing area

First layer of wall insulation being added in the crew changing area
28/11/21 RW