Work has continued through a dark December, often in cold and windy conditions. With temporary doors and plastic sheeting fitted to keep the weather out, most of the changes have been out of sight. Services are being installed with the underfloor heating system being much progressed. On the first floor crew room and facilities, a terracotta tiled floor has been added which will be heated by the ground-sourced heat pump system and uinderfloor pipework... a final floor covering will be placed over these tiles. Many of the interior walls are now visible though as yet lifts and final staircases are not in place.
The site has been tidied up and left looking smart for the Christmas break. Del's nursery in Fakenham kindly loaned a Christmas tree and we are grateful to Reside for making a stand and helping put it into position. The RNLI has also supplied a display Arancia-class lifeboat originally for the carol service but now doubling up as an added attraction over Christmas.
Monday 9 May 2022
Nearing completion...
Thursday 14 Apr 2022
Roof done and fitting out inside
Monday 28 Feb 2022
More external progress - walls and roof
Monday 31 Jan 2022
Beginning to look like a lifeboat station
Friday 31 Dec 2021
Working up to Christmas
Tuesday 30 Nov 2021
Internal works
Friday 29 Oct 2021
Steady progress
Monday 27 Sep 2021
Walls and floors
Wednesday 25 Aug 2021
Roof progress