Wells new Shannon boathouse
Wells Boathouse Build

New boathouse build

  Newer post...
Older post...  

Roof done and fitting out inside

Thursday 14 Apr 2022

The new boathouse build is gathering pace... perhaps not quite on the home straight but now very much in sight of it.

Externally, the biggest change is that the metal panelled roof has been installed. Temporary doors have also been removed revealing smart blue roller doors for the Shannon lifeboat, the inshore lifeboat and the southern access door which will be used for larger deliveries and equipment maintenance and changeovers. Vertical wooden battens have been added over the black insulation which will be followed by corner posts and horizontal battens onto which larch cladding will shortly be installed for the building's final exterior appearance.

Inside has been a hive of activity as different trades complete the fitting out. The temporary 'grand staircase' obstructing the boat hall has been removed and a metal staircase which the crew will use to get up to the Shannon boarding platform has been installed, along with the first stages of safety rails around the boarding platform and the public viewing platform opposite. Staircases up to the first floor crew room and to the public viewing gallery have been installed along with the two accompanying lifts. Fire sprinklers have been fitted in the boat hall along with powerful lighting around both the boat hall and inshore lifeboat area. Currently electric cables and sockets are being installed with plumbing and fittings for loos, showers and kitchen to follow.

The space at the top of the ALB ramp continues to be in demand, containers for the contractors having been removed but almost immediately replaced with a portacabin for Wells NCI Coastwatch while the normal lookout is refurbished. This is a temporary solution and will of course not be staying!

Despite the rapid progress, the schedule has slipped by a couple of weeks so we now expect the boathouse to be completed by mid-June rather than at the end of May. It is intended to open the building to the public, at least the visitor engagement and shop areas, as soon as possible and to begin the process of moving equipment and items across from the old boathouse. The inshore lifeboat will ideally be operating from the new building over this summer while the current Mersey-class all-weather lifeboat will, for now, continue to operate from the old boathouse. Our volunteer crew will soon formally start training for the Shannon lifeboat and it is likely that a relief Shannon lifeboat and SLARS launching carriage will come to Wells ahead of our actual new lifeboat 13-46 RNLB 'Duke of Edinburgh' which is set to arrive in the Autumn.

If you'd like to get involved with the new station, we are still looking for volunteers to help with visits and the shop and would be delighted to talk to you or meet you at our open day at Wells Sailing Club on 30th April (postponed from March).

 

Panels being added to main roof

Panels being added to main roof
9/3/22 RW

Completing the roof with insulation and battens prior to adding the exterior panelling

Completing the roof with insulation and battens prior to adding the exterior panelling
9/3/22 RW

Roller door for all-weather lifeboat revealed

Roller door for all-weather lifeboat revealed
13/3/22 MP

Roller door on south end revealed

Roller door on south end revealed
13/3/22 MP

Battens added to exterior walls ready for the final cladding to be installed

Battens added to exterior walls ready for the final cladding to be installed
22/3/22 MP

Window into ILB shed with finished roof panels

Window into ILB shed with finished roof panels
22/3/22 MP

New boathouse with roof almost complete

New boathouse with roof almost complete
23/3/22 John Fielding

New boathouse with roof almost complete

New boathouse with roof almost complete
23/3/22 John Fielding

Aerial view of old and new boathouses and outer harbour

Aerial view of old and new boathouses and outer harbour
23/3/22 John Fielding

Recovering the Mersey after an exercise by the new ALB ramp

Recovering the Mersey after an exercise by the new ALB ramp
10/4/22 MP

Gift shop and engagement space now with stairs and lift up to public viewing platform

Gift shop and engagement space now with stairs and lift up to public viewing platform
13/4/22 RW

Stairs and lift up to the crew room and office on the first floor

Stairs and lift up to the crew room and office on the first floor
13/4/22 RW

Crew changing area looking towards private changing space, shower and loo

Crew changing area looking towards private changing space, shower and loo
13/4/22 RW

Crew room being fitted out

Crew room being fitted out
13/4/22 RW

First floor landing with lift installed

First floor landing with lift installed
13/4/22 RW

Main boat hall with metal staircase up to the Shannon boarding platform installed

Main boat hall with metal staircase up to the Shannon boarding platform installed
13/4/22 RW

Boat hall with new stairs and railings and the temporary 'grand staircase' removed

Boat hall with new stairs and railings and the temporary 'grand staircase' removed
13/4/22 RW