Wells new Shannon boathouse
Wells Boathouse Build

New boathouse build

  Newer post...
Older post...  

Nearing completion...

Monday 9 May 2022

At long last, the building's exterior is beginning to look complete as larch cladding is added above the block work, covering the insulation layers. This was started on the north side by the crew room and changing area windows and progressed down the eastern side overlooking the beach and old lifeboat house.

The interior is transformed too with proper floors being put down, electrical work and plumbing in place and painting and decorating underway. There's still lots to do however and in particular the area to the south of the building and exterior steps and ramp to the entrance doors from the beach bank still need to be finished off and completed.

Overall, the project is still slightly behind its original schedule and we are now expecting it to be completed towards the end of June. The intention remains to open the public areas of the building as soon as possible and then to begin the process of moving from the old lifeboat house to the new. It is hoped that the inshore lifeboat will be able to move into and operate from the new building over the summer while the Mersey-class all-weather lifeboat will, for now, continue to operate from the current boathouse.

Our new Shannon class lifeboat should arrive in Wells in the Autumn, perhaps late September, and after some time for crew training will take over from the Mersey.

 

Larch cladding being added on eastern side

Larch cladding being added on eastern side
6/5/22 RW

Stairs up to public viewing platform

Stairs up to public viewing platform
6/5/22 RW

First floor facilities

First floor facilities
6/5/22 RW

ILB shed with finished floor surface and viewing gallery above

ILB shed with finished floor surface and viewing gallery above
6/5/22 RW

Boat hall with flooring and railings added to boarding and viewing platforms

Boat hall with flooring and railings added to boarding and viewing platforms
6/5/22 RW

Exterior cladding added to north wall

Exterior cladding added to north wall
6/5/22 RW

Final larch cladding being added to the building

Final larch cladding being added to the building
6/5/22 MP

View from the east with most of the cladding in place

View from the east with most of the cladding in place
6/5/22 MP

ALB ramp featuring temporary NCI Coastwatch portacabin while their lookout is refurbished

ALB ramp featuring temporary NCI Coastwatch portacabin while their lookout is refurbished
6/5/22 MP